NEW QUESTION # 39
You have chosen the "Advanced" option during the main configuration of the SUM tool. Which steps take place via the shadow instance?
There are 2 correct answers to this question.
Response:
- A. Switch to new repository (EU_SWITCH)
- B. Activation of dictionary objects (ACT_UPG)
- C. Modification adjustment (SPDD)
- D. Conversion of application tables (PARCONVJJPG)
Answer: B,C
NEW QUESTION # 40
Which of the following SUM activities require a stack XML file calculated by the maintenance planner?
Note: There are 3 correct answers to this question.
- A. SAP S/4HANA conversion including DMO
- B. DMO without system update
- C. Prerequisite check
- D. SAP S/4HANA conversion without DMO
- E. Benchmark tool
Answer: A,C,D
NEW QUESTION # 41
What SAP systems can you use for the ABAP Test Cockpit (ATC) to perform the custom code analysis for an SAP S/4HANA conversion? Note: There are 2 correct answers to this question.
- A. SAP ECC system from SAP ERP 6.0 EHP 8
- B. SAP S/4HANA Server 1809 and above
- C. SAP Solution Manager 7.2
- D. Standalone AS ABAP with SAP_BASIS 752 and above
Answer: B,D
NEW QUESTION # 42
Which steps should be performed during the adjustment of dictionary objects (SPDD) in the development system, before SUM continues?
There are 2 correct answers to this question.
Response:
- A. Create "modified* versions of the objects that you need to adjust
- B. Release the transport request containing the modification adjustment
- C. Assign the transport request as a modification adjustment transport
- D. Manually activate the adjusted dictionary objects
Answer: A,C
NEW QUESTION # 43
You are performing an upgrade with SUM. You are in the BIND_PATCH phase of the roadmap step
"Configuration". For some software components you find entries in the "Calculated level" column.
What does the "Calculated level" indicate for those software components?
Please choose the correct answer.
Response:
- A. The SAP Support Packages found in the download directory
- B. The SAP Support packages of the Support Package Stack, calculated by the Maintenance Planner
- C. The SAP Support Packages contained in the upgrade media
- D. The SAP Support Packages that will be bound to the upgrade
Answer: A
NEW QUESTION # 44
In ICNV. How database operations synchronized between the source and the target table?
- A. Deletes are directly executed in the target table by delete trigger.
- B. AA
Answer: A
NEW QUESTION # 45
The SUM procedure stops with an error during uptime. How can you identify the current phase, the one in which SUM encountered an error?
There are 2 correct answers to this question.
Response:
- A. Check the system log (transaction SM21) of the SAP system
- B. Check the messages shown by the SUM UI
- C. Check the most recent entries in SAPup.log
- D. Check the most recent entries shown in file sapevt.trc
Answer: B,C
NEW QUESTION # 46
What do you need to consider when performing the SI checks for an SAP S'4I 1ANA conversion? Note There are 2 correct answers to this question.
- A. You need an SAP system based on AS ABAP 7.50 or above for the SI check framework
- B. The SI checks are executed in the development system and the results are transported into the subsequent systems
- C. You need to build up an SI check framework by applying SAP Notes
- D. The errors from the SI checks must be solved, otherwise. SUM will report an error
Answer: A,C
NEW QUESTION # 47
How does SUM recognize modification adjustment transports from predecessor systems?
Please choose the correct answer.
Response:
- A. By searching for transport requests named <SID>K0<number>
- B. By searching for transport requests that are assigned to the project SAP_ADJUST
- C. By searching for transport requests in DIR_TRANS, subdirectory "transport"
- D. By searching for transport requests in the file umodauto.Ist
Answer: D
NEW QUESTION # 48
What do you do to prepare the database migration option of a SUM procedure?
There are 3 correct answers
Response:
- A. Extract the SAP HANA client installation archive
- B. Move the stack.xml update file into the download folder
- C. Extract the SAP HANA database installation archive
- D. Move the SAPM update archive into the download folder
- E. Move the R3trans update archive into the download folder
Answer: A,B,D
NEW QUESTION # 49
Which steps can SUM perform during an SAP S/4HANA conversion? Note; There are 2 correct answers to this question.
- A. Unicode conversion
- B. Software update
- C. Database migration
- D. Custom code analysis
Answer: B,C
NEW QUESTION # 50
During the SUM procedure, the phase XPRAS_AIMMRG fails. Where can you most likely see the reason for the error?
There are 2 correct answers to this question.
Response:
- A. In the latest log files in the SUM directory, subdirectory ABAP, subdirectory tmp
- B. In the latest log files in the SUM directory, subdirectory ABAP, subdirectory log
- C. In the job log for the corresponding job in SM37 (Job Overview)
- D. In the corresponding R3trans log files of this phase
Answer: B,C
NEW QUESTION # 51
What do you need to consider when performing the SI checks for an SAP S/4HANA conversion? There are 2 correct answers to this question.
- A. Depending on the SAP S/4HANA version, there are different SI check frameworks.
- B. You need to build up a SI check framework by applying SAP notes.
- C. The SI checks are executed in the development system and the results are transported into the subsequent systems.
- D. You need an SAP system based on AS ABAP 7.50 or above for the SI check framework.
Answer: A,B
NEW QUESTION # 52
You are planning to upgrade your SAP ECC 6.07 system running on a single codepage (SCP) to SAP ECC
6.08. What is the recommended option to perform this upgrade?
Please choose the correct answer.
Response:
- A. Combine the upgrade and the Unicode conversion using the Combined Upgrade &Unicode Conversion (CU &UC) procedure.
- B. Combine the upgrade and the Unicode conversion using the Twin Upgrade &Unicode Conversion (TU
&UC) procedure. - C. Perform the upgrade to SAP ECC 6.08 before the Unicode conversion.
- D. Perform the Unicode conversion before the upgrade to SAP ECC 6.08.
Answer: D
NEW QUESTION # 53
During a SUM run you want to check if the phase SHADOW_IMPORT_INC is still running properly. Where can you find information about this?
There are 2 correct answers to this question.
Response:
- A. Check for running batch jobs in the shadow system via Job Overview (SM37)
- B. Check for running R31oad processes on the host of the primary application server
- C. Check for the latest log files in the SUM directory, subdirectory ABAP, subdirectory tmp
- D. Check for running R3trans processes on the host of the primary application server
Answer: C,D
NEW QUESTION # 54
You are running an SAP ECC system.
For which of the following activities does SUM allow you to use the near-Zero Downtime Maintenance (nZDM) capabilities?
Note There are 3 correct answers to this question
- A. Perform an SAP S/4 HANA conversion including DMO
- B. Use DMO for SUM
- C. Upgrade the SAP system
- D. Perform an SAP S/4 HANA conversion without DMO
- E. Apply SAP support packages
Answer: B,C,E
NEW QUESTION # 55
During a DMO procedure with SUM, after which phase is the repository first available on the target database?
Please choose the correct answer.
Response:
- A. ParaUel distribution (PARDIST_SHD)
- B. Shadow repository creation (EU_IMPORT*)
- C. Downtime migration (EU_CLONE_MIG_DT_RUN)
- D. Uptime migration (EU_CLONE_MIG_UT_RUN)
Answer: D
NEW QUESTION # 56
Which of the following are valid options to check the progress of an inplace SUM DMO run? Note There are 2 correct answers to this question
- A. Check the dump size of the database export on disk.
- B. Check logs for jobs starting with RSUPG_SGEN in the SAP system.
- C. Check the Charts Control Center in the SUM Ul
- D. Check the log files written in the SUM directory subdirectory abap. subdirectory log
Answer: A,D
NEW QUESTION # 57
When using the DMO of SUM, which files can be handled by SUM in the download directory?
There are 2 correct answers to this question.
Response:
- A. Parameter file SAPup_add.par
- B. MIGRATE J5T_DUR_XML file from a previous run
- C. Stack XML file calculated by the Maintenance Planner
- D. Breakpoint configuration file SAPUPPHAS.BRK
Answer: B,C
NEW QUESTION # 58
Which additional configuration options are offered by SUM when selecting "Switch expert mode on" in main configuration option "Standard"?
There are 2 correct answers to this question.
Response:
- A. Use the Near Zero Downtime Maintenance Technology (NZDM).
- B. Reuse a profile for the shadow instance from a previous run.
- C. Choose the instance number of the shadow instance.
- D. Keep archiving on during the whole procedure.
Answer: B,C
NEW QUESTION # 59
Which Guides contain information about SUM phases starting with "EU_CLONE_"?
There are 2 correct answers to this question.
Response:
- A. The Application Guide
- B. The DMO Guide
- C. The SAP S/HANA Conversion Guide
- D. The major SUM Guide
Answer: B,C
NEW QUESTION # 60
You are executing a standard SUM procedure to update an SAP system using main configuration mode "Standard". When will the shadow system be stopped for the last time?
Please choose the correct answer.
Response:
- A. Early in the downtime
- B. As part of the cleanup process
- C. At the end of the downtime
- D. Before the downtime starts
Answer: D
NEW QUESTION # 61
You are executing as SAP S/4HANA Conversion with scenario strategy Standard. When will the shadow instance be stopped for the last time?
- A. Early in the downtime
- B. Before the downtime starts
- C. As part of the cleanup process
- D. At the end
Answer: D
NEW QUESTION # 62
You are planning to use DMO of SUM to perform an "inplace-migration" to SAP HANA. What do you need to consider? Note: there are 2 correct answers to this question.
- A. The source system is non-Unicode and the target database is a scale-out system.
- B. The target database size increases temporarily because of the Shadow Repository.
- C. Network capacity between exporting and importing R3load processes must be.
- D. Unicode conversion is part of DMO only in case of target version AS ABAP 7.40 or 7.31.
- E. SAP HANA Landscape Reorganization required a manual step to edit a file.
Answer: D,E
NEW QUESTION # 63
What is the main purpose of performing benchmark runs for an SAP S/4HANA conversion?
- A. To optimize the conversion
- B. To optimize the activation
- C. To optimize the migration
- D. To optimize the main import
Answer: C
NEW QUESTION # 64
......
Latest SAP E_S4HCON2023 Real Exam Dumps PDF: https://www.validvce.com/E_S4HCON2023-exam-collection.html
E_S4HCON2023 Exam Dumps, E_S4HCON2023 Practice Test Questions: https://drive.google.com/open?id=1vYqzyg7pExetC0SggO1WJubFVB0k1bOa