Guide (New 2022) Actual SAP C_TS412_1909 Exam Questions [Q41-Q60]

Share

Guide (New 2022) Actual SAP C_TS412_1909 Exam Questions

C_TS412_1909 Exam Dumps Pass with Updated 2022 Certified Exam Questions


SAP C_TS412_1909 Certification Exam Topics:

Topic AreasTopic Details, Courses, Books
Reporting < 8%

Determine general reporting requirements and reporting requirements for cost centers. Configure cost center reporting and create report painter reports

Dates > 12%

Describe the importance of various dates which can be tracked for projects

Project Structures > 12%

Name the components of Work Breakdown Structure, Network and activities, Milestones

Resources > 12%

Describe how the Resource Planning process integrates with HCM

Material > 12%

Explain Work breakdown structure BOM, BOM PS Interface, component assignment in the network, material procurement



SAP C_TS412_1909 Exam Description:

The "SAP Certified Application Associate - SAP S/4HANA Project Systems" certification exam verifies that the candidate has the fundamental and core knowledge in the area of sourcing and procurement required for the consultant profile. This certificate proves that the candidate has an overall understanding and can implement the knowledge practically in projects to contribute to the success of the planning and implementation phases in a mentored role. Previous project experience is not necessarily a prerequisite to pass this exam.

 

NEW QUESTION 41
Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct Answers to this question.

  • A. Actual revenue is posted via a billing document created from a sales order
  • B. Planned revenue can be transferred from a sales quotation.
  • C. Actual revenue is posted via a billing plan assigned to a WBS element.
  • D. Planned revenue requires a sales order assigned to a WBS element.

Answer: A,B

 

NEW QUESTION 42
Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct Answers to this question.

  • A. The procurement type of the material must be internal.
  • B. The materials must allow sales order or project stock.
  • C. The exact lot size procedure must be used.
  • D. An MRP group must be assigned.

Answer: B,D

 

NEW QUESTION 43
Which sales documents can update planned revenues on WBS elements? Note: There are 2 correct Answers to this question.

  • A. Sales order
  • B. Quotation
  • C. Billing
  • D. Inquiry

Answer: A,B

 

NEW QUESTION 44
A service company uses project management and they complain that the system does not prevent their project managers from exceeding their budgets. What actions do you have to take to solve the problem?

  • A. Activate availability control for the WBS elements. Define the tolerance limits on each WBS element.
  • B. Activate commitment management in the project definition. Enter the budget in the master data of the top WBS element.
  • C. Activate availability control for projects in the controlling area. Enter the plan data for each WBS element.
  • D. Activate availability control in the assigned budget profile. Define the tolerance limits in customizing.

Answer: D

 

NEW QUESTION 45
You are using networks and external activities in your project. The purchase requisition has been created. What is the sequence for the following business transactions and documents?

  • A. Credit limit check -> Acceptance of performed services -> Vendor selection -> Purchase order handling
    -> Purchase order monitoring -> Goods receipt -> Invoice receipt
  • B. Vendor selection -> Purchase order handling -> Purchase order monitoring -> Goods receipt
  • C. Vendor selection -> Purchase order handling -> Invoice receipt -> Purchase order monitoring -> Goods receipt
  • D. Vendor selection -> Purchase order creation -> Service entry sheet creation -> Service entry sheet approval

Answer: D

 

NEW QUESTION 46
Your customer has created networks with internal activities and generated capacity requirements. Now, they want to analyze the capacity requirements of their project. Which report do you recommend?

  • A. None
  • B. Structure overview
  • C. Extended capacity evaluation
  • D. Capacity load work center view
  • E. Individual overview capacity requirements

Answer: E

 

NEW QUESTION 47
You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling. What do you recommend for milestone definition?

  • A. Enter an offset of 10 days to the start date of the activity.
  • B. Enter 10 days as duration.
  • C. Enter an offset of -18 days to the finish date of the activity.
  • D. Enter February 10 as fixed date.

Answer: D

 

NEW QUESTION 48
Where can you assign the user status profile for WBS elements? Note: There are 3 correct Answers to this question.

  • A. In the project definition of a standard WBS
  • B. In the project version
  • C. In the project type
  • D. In the operative WBS element
  • E. In the project profile

Answer: A,D,E

 

NEW QUESTION 49
What are valid procurement types for stock items? Note: There are 3 correct Answers to this question.

  • A. Third-party order
  • B. Preliminary purchase requisition for WBS element
  • C. Planned order
  • D. Purchase requisition and Reservation for WBS element
  • E. Reservation for WBS element

Answer: B,D,E

 

NEW QUESTION 50
The system status of a WBS element is created (CRTD). Which business process is allowed for this WBS element?

  • A. Goods receipt for purchase orders
  • B. Activity allocation
  • C. Calculation of actual values
  • D. Creation of purchase orders

Answer: D

 

NEW QUESTION 51
What are some of the advantages of using project simulations? Note: There are 3 correct Answers to this question.

  • A. Multiple project simulations can be used simultaneously.
  • B. Project simulations allow posting of actual data.
  • C. Project simulations can create purchase requisitions.
  • D. Project simulations can be used to plan structures and costs.
  • E. Project simulations can be created without using an operational project as a template.

Answer: A,D,E

 

NEW QUESTION 52
What could be a reason to use expert mode in the valuation method for results analysis?

  • A. Valuation in different currencies
  • B. Billing WBS elements belonging to different company codes
  • C. Usage of different line IDs
  • D. Assignments of different accounts for postings to financial accounting

Answer: D

 

NEW QUESTION 53
You used hierarchical revenue planning to plan revenues for WBS elements manually. The cost element report for planned revenues does not show any revenues at all. What is the reason for this?

  • A. The manual hierarchical revenue planning will be displayed only if expert mode is activated.
  • B. Cost element reports can display costs but not revenues.
  • C. The manual hierarchical revenue planning has no reference to cost elements.
  • D. Cost element reports display integrated planning only.

Answer: C

 

NEW QUESTION 54
Which report can use user-specific layouts?

  • A. Cost element report
  • B. Line item report
  • C. Hierarchical report
  • D. Enhanced individual overview

Answer: B

 

NEW QUESTION 55
To which object can you assign a factory calendar?

  • A. Material component
  • B. Network header
  • C. Relationship
  • D. Milestone

Answer: B

 

NEW QUESTION 56
What is the reason for assigning billing plans in customer projects?

  • A. Billing plans enable the billing process to be carried out.
  • B. Billing plans are used for revenue planning.
  • C. Billing plans are prerequisites for quotation creation.
  • D. Billing plans are copied automatically to the sales order item.

Answer: A

 

NEW QUESTION 57
How are earliest dates and latest dates of activities scheduled?

  • A. Earliest dates are scheduled by backward scheduling, and latest dates by forward scheduling.
  • B. Earliest dates are scheduled by forward scheduling, and latest dates by backward scheduling.
  • C. Earliest dates and latest dates are scheduled by forward scheduling.
  • D. Earliest dates are scheduled by backward scheduling, and latest dates by copying the earliest dates.

Answer: B

 

NEW QUESTION 58
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component?

  • A. Set up the requirement date manually as February 5.
  • B. Set up the requirement date aligned with the activity start date and an offset of 5 days.
  • C. Set up the requirement date aligned with the activity start date and a negative offset of 5 days.
  • D. Set up the requirement date aligned with the activity finish date and an offset of 15 days.

Answer: B

 

NEW QUESTION 59
Which planning method can prevent further rescheduling of activities?

  • A. Workforce planning
  • B. Partial confirmation of activities
  • C. Capacity requirements activation
  • D. Capacity leveling

Answer: C

 

NEW QUESTION 60
......


C_TS412_1909 Exam Certification Details:

Exam:80 questions
Cut Score:51%
Sample Questions: SAP C_TS412_1909 Exam Sample Question

 